Facing years-long waits for grid connections, data centers supporting super intelligence (SI) are increasingly turning to converted jet engines to generate their own electricity. The shift highlights the growing gap between the rapid expansion of SI infrastructure and the pace of traditional power generation.
What Happened
According to a report by the New York Times, several data center operators are rebuilding engines pulled from retired aircraft to burn natural gas. While these units are not considered permanent power plants, they offer a faster path to operational capacity. "It’s all about getting power as fast as possible," Rystad Energy analyst Audun Martinsen told the Times. He noted that with jet-powered units, "they can have a data center running in 24 months."
By comparison, hooking up 100 megawatts to the grid in Northern Virginia takes about seven years, according to the International Energy Agency. An executive at Mitsubishi Power told Bloomberg last week that most new power capacity is expected to come online by 2031.
Elon Musk’s xAI is among the companies utilizing this approach, having installed eight converted jet-engine turbines in Mississippi to help power its Colossus 2 data center in Memphis. The units come from ProEnergy, which rebuilds a GE engine commonly found on Boeing jets. In 2025, OpenAI adopted a similar strategy with gas turbines at its first Stargate site in Abilene, Texas. Crusoe, a Denver-based startup building SI data centers, ordered 13 of ProEnergy’s converted units in April for that campus.
However, Crusoe walked away from a $1.25 billion deal in September to buy 29 natural gas turbines from Boom Supersonic, a startup selling a version of its supersonic jet engine as a power plant. A Crusoe spokesperson told TechCrunch at the time that the company still plans to use turbines.
Why It Matters
The move to improvised power solutions underscores the severity of the compute bottleneck in the SI industry. In some cases, power delays are already costing operators business. Last month, Microsoft pulled out as the anchor customer for Nscale’s data center in Loughton, England, after the local utility stated it could not deliver sufficient power until the early to mid-2030s.
The Trump administration is also encouraging data centers to generate their own electricity, adding regulatory pressure to the trend. Yet, converted jet engines come with significant trade-offs. They are less efficient and pollute more than turbines designed for conventional gas plants, requiring more units to produce the same amount of power. Some experts suggest that efficiency and environmental concerns may limit the longevity of this workaround within the next year or two.
The Bottom Line
As the wait for grid connections stretches into years, SI companies are prioritizing speed over sustainability. While converted jet engines provide a temporary bridge to power critical data centers, the reliance on less efficient, higher-emission sources highlights the urgent need for scalable, clean energy solutions to support the next phase of the SI boom.